Skip to content
Rhosus Energy
Insights

Grid congestion and battery storage: when does a battery help?

Grid congestion means that the electricity grid is full at a given place. New connections and extra capacity then go on a waiting list, which can run to 10 years in full areas. A battery on an existing connection does not make the grid bigger, but it does use the space your wind or solar park leaves unused, provided the grid operator cooperates and the battery does not add load to the grid.

Updated:

What is grid congestion?

The grid is congested when it cannot carry any more power at busy moments. Dutch grid operators' association Netbeheer Nederland distinguishes congestion for feed-in (power onto the grid, for example from a wind turbine or solar park) and for offtake (power from the grid). In many places there is no room left in one or both directions.

The capacity map of Netbeheer Nederland shows the status per area, for offtake and feed-in separately. There are four statuses: transport capacity available without a queue, limited capacity without a queue, area under investigation with a queue, and shortage of transport capacity with a queue.

For new projects this often means a wait of several years. For existing projects it can mean that the grid operator asks them to feed in less at busy moments, either for a fee or as a condition of the connection.

How big is the problem?

According to Netbeheer Nederland (Stand van de Uitvoering 2025, April 2026), at the end of 2025 the regional grid operators had about 15,000 offtake requests on the waiting list, together 9,305 MW. For feed-in there were about 8,700 requests, together 5,027 MW. At TenneT, the national grid operator, there were 210 offtake and 168 feed-in requests.

The number of offtake requests at the regional operators kept growing: from about 12,000 a year earlier to 15,000. Netbeheer Nederland writes that flexible use of the grid is lagging behind what is needed to really shorten waiting times.

How does the waiting list work?

Anyone who requests a new connection, a heavier connection or more contracted capacity first receives a quote. If there is no room in your area, the request goes on the waiting list once you sign that quote.

The waiting list applies per congestion area, not nationally. The basic rule is first come, first served. Parties with priority rank higher but must ask for it themselves. When space becomes available, the grid operators allocate it under the ACM's prioritisation framework. How long it takes depends on grid reinforcement in your area. In full areas it can take up to 10 years, according to Netbeheer Nederland.

Why an existing connection is so valuable

An existing connection is something newcomers can no longer get. At a wind turbine or solar park, the connection is used at full capacity only part of the time: at night or when there is no wind it is barely used. Our own solar park in Dalfsen used just 9% of the capacity of its 6 MW connection in 2024.

A battery on the same connection can use that spare capacity. It charges when there is a surplus or when power is cheap, and discharges when there is demand. The connection stays within the contracted capacity you already have.

If you give up a connection, you lose that space. A new request in a congested area goes on the waiting list.

How does a grid operator connect a battery?

This differs per grid operator. Enexis, for example, connects batteries above 1 MW only in a congestion-neutral way. For that you sign a capacity control contract (CSC) in addition to the connection and transport agreement. Enexis can then impose a limit the day before the grid is expected to become full, and the battery must be remotely controllable.

If your connection already has enough transport capacity, Enexis says you do not need a new control contract, but in most cases you do have to report the battery. If that capacity is missing, a request for a heavier connection goes on the waiting list.

The ACM has also introduced new transport rights for users with flexible grid use. The time-duration transport right on TenneT's high-voltage grid guarantees transport for at least 85% of the hours in a year, at a lower grid tariff. The time-block right works on the regional grids, within agreed time blocks. The ACM names battery storage explicitly as an example of a flexible grid user. At the end of 2025 there were 162 contracts for such alternative transport rights.

When does a battery help?

A battery is not the answer for every project. It works well when several things come together:

  • There is an existing or committed connection with unused capacity.
  • The grid operator allows the combined use, possibly with arrangements for peak moments. In a congested area, sharing a connection may not increase the existing transport capacity.
  • There is a revenue model that suits the site: trading on the day-ahead and imbalance markets, ancillary services such as aFRR, or absorbing the site's own peaks.
  • The permit and spatial fit are achievable. A battery usually needs an environmental permit (omgevingsvergunning).

What a battery does not solve

A battery on an existing connection does not make the grid bigger. If you want more capacity than your contract allows, you still have to wait until the grid is reinforced. A new, separate connection for a battery alone also joins the same waiting list as everyone else in a full region.

Netbeheer Nederland also stresses that alternative transport rights are not meant to cut the peaks but to fill the valleys. The gain lies in using the moments when there is room. A battery on a connection that already has spare capacity fits that.

How we assess it

Our platform Powerplaats shows, per supply area, the room for feed-in and offtake, and how it has changed since the previous capacity map. It also shows which solar, wind and battery permits have been granted or applied for nearby.

With that, we model a battery for the site: how much power and storage fit, how the battery is dispatched, and what the grid limits mean. Our models are checked against metered data from batteries in operation.

Frequently asked questions

What is grid congestion?

Grid congestion means the electricity grid is full at a given place. There is then no room for extra feed-in (power onto the grid), extra offtake (power from the grid), or both. New requests go on a waiting list.

Can I install a battery in a congested area?

On an existing connection with enough transport capacity, often yes, if the grid operator allows it and you report the battery. A heavier or new connection joins the waiting list in a full region.

Does a battery help against grid congestion?

A battery can make better use of the space on an existing connection, but it does not make the grid bigger. Enexis, for example, therefore connects large batteries only in a congestion-neutral way.

How long is the waiting list for grid capacity?

That differs per congestion area. In full areas it can run up to 10 years, according to Netbeheer Nederland, because it depends on grid reinforcement.

How can I see whether my area is full?

The capacity map of Netbeheer Nederland shows the status per area for offtake and feed-in. Our site check looks at that together with your connection.

How we work with owners of wind turbines and solar parks

Want to know what this means for your project? Read about our feasibility scan for your battery project, or about grid capacity and permits per area in Powerplaats.

Contact

Make better use of a connection?

We take a free first look at the grid situation and the options for a battery at your site.

How can we help?

Battery, lease or power purchase after the SDE

Enter an email address or a phone number. We are happy to call you back.

We only use your details to respond to your enquiry. Read our privacy statement.

Waiting for verification…

CallSite check